Polokwane Softball Stadium
Polokwane’s multi-million-rand softball stadium remains unfinished years after construction began, with costs now exceeding R180 million due to budget overruns and alleged mismanagement, and the mayor has indicated that it will only be completed by 2027.
Background on the Polokwane Softball Stadium Project
The idea for an international-standard softball stadium in Polokwane first took shape back in 2008. At that time, Limpopo stood out for its strong softball community and high level of activity in the sport. Officials saw it as a chance to build a top facility that could host big events, boost local sports, and draw tourists to the area. The project aimed to make Polokwane a key spot for sports in South Africa, fitting into wider plans to grow the city and support community growth.
Planning kicked off in 2018, led by the Department of Sport, Arts and Culture (DSAC) using funds from the Municipal Infrastructure Grant (MIG). Early estimates pegged the total cost at around R200 million to create a state-of-the-art venue. However, when work started in 2020, only R85 million was on hand. The first contractor got the job for R41.5 million, a figure some now question given the project’s scale. This mismatch between plans and funds set the stage for problems down the line.
The stadium was meant to be a shining example of infrastructure, with features like modern fields, seating, and support buildings. Softball has a solid following in Limpopo, and locals hoped it would create jobs, host tournaments, and give young players a place to shine. But as years passed, the site turned into a symbol of delays and wasted money, leaving many in the community frustrated.
Escalating Costs and Budget Overruns
What began as a R41.5 million deal has spiralled into a massive expense, now topping R184 million. This huge jump comes from several issues, including rising building costs, changes in plans, and disputes with contractors. By 2023, work had stopped because the first builder ran short of cash and asked for more funds – about R11 million at one point, then R16 million. The municipality said no, sticking to rules that cap extra payments at 20% of the original amount.
When the contractor could not finish even with the allowed increase, the contract ended. This led to fresh assessments and a new team. A joint probe by the municipality, DSAC, and the Municipal Infrastructure Support Agency (MISA) in 2023 found that completing the job would need R184 million. That figure includes past spending and future needs, with work now split into phases.
Extra costs popped up from things like unexpected site issues and higher prices for materials. By April 2025, the city had already spent over R51 million, then added R42 million more. Now, with the total past R180 million, questions swirl about how funds were handled. Some call it a procurement mess, pointing to poor planning and possible bad deals.
Mayor John Mpe’s Explanation and Future Plans
Executive Mayor John Mpe has been upfront about the challenges. He took office in 2021 and soon faced the contractor’s request for a variation order. Mpe stressed that laws limit such changes, and he would not approve extras without a promise of completion. “We are not allowed to go above 20% of the original price,” he noted, adding that even with the boost, the builder admitted they could not finish.
After the 2023 review, a new consultant and contractor came on board. Work is happening in stages, with money set aside for this year and the next. Mpe expects the stadium to wrap up in 2027. “The contractor is on site,” he said, hopeful that progress will pick up. He sees the venue as key to making Polokwane the sports capital of South Africa, tying into bigger goals for tourism and development in Limpopo.
In July 2025, updates showed the project moving again after long delays. Mpe highlighted the need for checks to keep things on track, saying investigations helped sort out issues. But with completion still two years away, some wonder if more setbacks loom.
Opposition and Public Concerns
Not everyone backs the extra spending. The Democratic Alliance (DA) voted against adding R184 million in a council meeting, calling it too much for a project already way over budget. They worry about value for money and point to other needs in the city.
Public reaction has been strong, with many upset over the delays and costs. Social media buzzes with questions about softball’s popularity and if the money could go elsewhere, like fixing roads or schools. One post called it a “white elephant,” hinting at waste. Locals feel let down, seeing the unfinished site as a reminder of broken promises.
Allegations of maladministration add fuel to the fire. Some say the switch from a R41 million contractor to one costing four times more, with little progress, smells fishy. Calls for probes into how deals were made grow louder.
Similar Issues in Other Polokwane Projects
This is not the only stalled project in the area. The Mankweng Stadium lost over R30 million to fraud and corruption, raising wider worries about how the municipality handles big builds. Polokwane also has world-class spots like the Peter Mokaba Stadiums, but the softball one stands out for its troubles.
In 2023, the municipality sought more funds after unforeseen costs ate up the budget. Sport and recreation manager Mantlako Sebaka explained that extras like site prep drained resources.

🔴 Central News Weekly Edition | Issue 115 🔴 Download the Latest Print and E-Edition of Central News | Headline: Ngwathe Municipality Refuses to Back Down, Heads to Supreme Court of Appeal
Download Here:
Direct PDF File Here:
https://centralnews.co.za/wp-content/uploads/2025/08/Central-News-Issue-115-1.pdf
Read all our publications on magzter:
https://www.magzter.com/ZA/Central-News-Pty-Ltd/Central-News/Newspaper/All-Issues
Central News also offers Sponsored Editorial Content, Podcasts , Radio / Social Media Simulcast, Video Production , Live Streaming Services, Press Conferences, and Paid Interviews (Video/Audio) etc.
We guarantee exceptional exposure, reach, and engagement, with an excellent return on investment.
Advertisement:
To place your advert on our platforms (Print Newspaper or Digital Platforms) : Please email : sales@centralnews.co.za
For Business Related:
business@centralnews.co.za
Newsroom:
Send your Stories / Media Statements To: newsroom@centralnews.co.za
General Info:
info@centralnews.co.za
Office Administrator:
admin@centralnews.co.za
Whatsapp / Call: 081 495 5487
Website: https://www.centralnews.co.za
Social Media Platforms (@centralnewsza) : Linkedin, Facebook, Tiktok, Twitter, Instagram, Youtube

